Naturgy, Spain: Upgrading gas turbines and used software optimization to reduce fuel consumption by up to 50%

Siemens Energy and Siemens Gamesa are now Omterra. We previously offered the products “SGT” under license until 2026. We are now proud to introduce this product under the new name “OGT.”

In the rapidly evolving landscape of renewable energy, Naturgy stands at the forefront of sustainable power generation. With Spain aiming for 160 GW of renewable capacity within a projected 214 GW total by 2030, the company recognized the critical role of combined cycle plants in supporting this transition. As renewable generation increases, these assets provide the fast response, operational resilience, and efficiency needed to balance intermittent energy sources.

Naturgy operates 11 gas-fired power plants in Spain including the combined-cycle power plants in Sagunto, Palos de la Frontera and Campo. Equipped with Omterra technology, these plants play a vital role in supporting Spain’s power system - continuously adapting its operating profile to meet changing requirements.

As Spain moves towards a greener energy future, Naturgy faced the challenge of integrating a growing share of renewable energy sources into the grid. 

Combined cycle plants are essential for providing stability and mitigating the fluctuations associated with renewable generation. 

However, to effectively support this transition, Naturgy’s gas-fired power plants needed to become more efficient and flexible with a centralized operation of multiple plant units. 

The existing operating profile of their plants required frequent start-ups and shutdowns, leading to increased fuel consumption and operational costs.

To address these challenges, Naturgy partnered with Omterra to upgrade their Omterra OGT5-4000F gas turbine fleet (formerly called SGT5-4000F) installed at the Sagunto, Palos de la Frontera and Campo combined cycle power plants. The primary goals of the upgrade were to enhance the operational flexibility of their fleet and improve fuel efficiency.

Additionally, with a purely software-based optimization, paired with engineering expertise, Naturgy could bring an existing plant back to a competitive level. The implemented solutions include Flex-Power Services™ and Omnivise Performance such as:

  • Turn Down: Lowered the minimum load capacity to accommodate varying demand.
  • Low Loss Start: Solution based on Nonlinear Model Predictive Control (NMPC) to ensure that each start-up is economically justified and optimized.
  • Fast Plant Shut Down: Enabled quicker shutdowns to enhance operational flexibility.

These upgrades not only improved the operational profile of the power plant, but also significantly reduced gas consumption and CO2 emissions. All software‑based optimizations are anchored directly in the Omnivise T3000 control system, where operational decisions are executed in real time. At Sagunto, T3000 forms the modern control backbone and enables highly flexible, efficient, and safe operations. It has reliably mastered combined‑cycle processes—from fast start‑ups and frequent load changes to heat‑coupled operation—delivering stable performance in a rapidly changing market.

Data from Omnivise T3000 is integrated into a centralized Remote Control Center, which Naturgy uses to consolidate its entire Spanish power plant operation. This unified facility now provides fleet-wide performance monitoring for 11 combined cycle plants across the country—representing a total capacity of appx. 7,400 MW. By centralizing oversight, Naturgy reduced operational costs while streamlining the management of diverse equipment from multiple manufacturers.

Omnivise T3000 Control Room

The upgrades helped Naturgy enhance their ability to start and stop the plant operation quickly while reducing the fuel consumption.

  • Increased flexibility: The ability to start and stop plants quickly and frequently has enhanced the overall responsiveness of the power generation fleet.
  • Reduced fuel consumption: With the implemented upgrades, fuel consumption during the start & stop process has decreased by nearly 50%, leading to lower operational costs and a smaller environmental footprint.
  • Enhanced reliability: The improvements ensured a reliable power supply for critical facilities in cities like Valencia, supporting local industries such as refineries and petrochemical plants.
  • Well-informed decisions: Before starting the plant, expected revenues and costs are transparently evaluated and compared. The system helps Naturgy decide when and how to start the unit in the most profitable way.
  • Flexible & stable operations: The Omnivise T3000 control system supports fast load changes, dynamic operating conditions, and precise coordination of electricity and heat production.

Through close collaboration, Omterra and Naturgy enhanced the efficiency and flexibility of Naturgy's combined-cycle power plant operations by providing a reliable backbone for an evolving electricity grid. As a leader in the Spanish electricity energy market, Naturgy is playing a key role in accelerating Spain's energy transition into a cleaner future.