Monitoring and re-adjustment of all functions of the monitoring, safety and protection equipment. Opening of the turbine housing not necessary.
Aquision and assessment of the actual turbine condition by testing during operations and during the cool down phase:
In addition to the inspection‘s scope of work, during the minor overhaul further testings but also necessary replacements are executed. Opening of the turbine housing not necessary.
Acquisition of the actual turbine condition including necessary testings and replacements. Testings of:
Additional to the scope of inspection and minor overhaul, during the major overhaul the turbine is examined in dismantled condition. Opening of the turbine housing necessary.
Acquisition of the actual turbine condition inclding necessary testings and replacements. Testing and controling of:
Approximately 18 months in advance, a meeting with a Omterra service engineer is necessary to clarify the following scope of work under consideration of plant observations, operating behaviour and EOH:
By utilization of an optimized maintenance strategy the following benefits can be ensured: